The transformer delay that nearly sunk my biggest job last year

Last year, I handled a commercial job needing a special 75kVA transformer. The vendor promised delivery in a month, so I scheduled around it. Delays hit when they said it was stuck in port. My crew sat idle for over a month, angering the general contractor. We missed out on other work because of the hold. After two and a half months total, it arrived damaged, requiring more delays. Now I get lead times in writing and line up backups. Don't get trapped like I did.
3 comments

Log in to join the discussion

Log In
3 Comments
derek_bailey84
Tough spot, but that's on your scheduling.
0
blair_webb
blair_webb1mo ago
Explain what you mean by that.
5
jasonf17
jasonf171mo ago
Actually think you might have the wrong idea here. The schedule was set months ago and approved by everyone. The tough spot came from a last minute change nobody could have predicted. It's not really about planning, more about bad luck hitting at the worst time.
2